Level Crossing at Pachanadi to Remain Closed For Road Traffic From October 10: More Information

Level Crossing at Pachanadi to Remain Closed For Road Traffic From October 10: More Information

To facilitate the work of the final leg of the RoB construction and re-grading and concreting of approach roads at both Bondel and Vamanjoor sides of the project which is scheduled to be taken up between October 10 and November 10, the level crossing (No. 6A) at Pachanady will remain closed for road traffic from October 10. The vehicles will be diverted to alternate route. The light four-wheelers can take the alternative route via PWD Bund Road originating from Pachanady. Heavy vehicles like buses and trucks may ply through Kulshekhara to reach Vamanjoor from Bondel. The 27.95m long and 12m wide RoB is being built at an estimated cost of Rs 5 crore utilising funds from the track-doubling project.